Phase 1: Update for the Weeks of March 30 & April 6, 2025
March 27 to March 29, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities: Installation of keeper blocks…
Phase 2: Update for the Weeks of March 23, 30, and April 6 and 14, 2025
DAY WORK: During weekdays, Monday, March 24 through Friday, April 11, from 6:00 AM to 3:30 PM crews will conduct a variety of work…
Phase 1: Update for of Feb. 16 & 23, and March 2, 2025
February 20 and February 21, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities: Drainage activities on the…
Phase 1: Update Weeks of January 19 & 26, and February 2, 2025
January 23 and January 24, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities: Grading and stoning the…
Wrong Way Detection Installation on I-691 EB at Exit 3 in Meriden – Dec. 2 – 6.
The Connecticut Department of Transportation (CTDOT) is announcing a wrong way detection installation will take place on I-691 east bound at in Meriden. This…
Phase 2: Update for the Weeks of September 23 and 30, 2024
NIGHT WORK For the weeks of September 23 and 30, 2024, expect work from 8:00 PM to 6:00 AM (Sunday through Thursday nights –…
Detour: Route 15 NB Exit 67 to East Main Street in Meriden Detour Route Map
Check the Construction Alerts page for the current week to see if this detour is in place at this time. Route 15 NB Exit…
Detour: Route 15 NB Exit 68 N-E to I-91 NB and Route 66 EB Detour Route Map
Check the Construction Alerts page for the current week to see if this detour is in place at this time. Route 15 NB Exit…