DAYTIME WORK:

Monday through Friday from 7:00 AM to 3:30 PM crews will conduct a variety of work as noted throughout the Phase 3 Project limits:

  • Maintain water handling at multiple sites of culvert rehabilitation
  • Culvert rehabilitation at multiple sites
  • Haul in stockpile supplemental streambed material and install at required sites
  • Sawcut, excavate, and backfill in the I-91 SB median from north end of project limits to Exit 17 for the added lane
  • Sawcut, excavate, and backfill in the I-91 SB right shoulder and Route 15 SB median
  • Excavate for and install support of excavation, and partial demolition of the Route 15 SB ramp bridge to I-91 SB over the I-91 SB ramp to Route 15 SB
  • Demolition of Murdock Avenue pier and excavate for pier footing
  • Removal of existing masonry and installation of parapet caps, curb and deck ends on the I-691 EB Bridge over Gravel Street
  • Construction staking sitewide
  • Joint repairs and sealing culverts at multiple bridges
  • Install drainage in Route 15 SB median near Paddock Avenue
  • Install drainage on I-91 SB median north end at the East Main Street ramp to I-91 SB

DAYTIME LANE CLOSURES: Sunday through Thursday from 8:00 AM to 2:00 PM:

  • I-91 SB lane closures (Murdock Avenue to Exit 15) for shoulder reconstruction

NIGHTTIME WORK:

Sunday through Friday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work as noted:

  • Pave top courses on I-91 SB from Murdock Avenue to the southern end of the project limits
  • Maintenance of existing illumination
  • Line striping for I-91 SB
  • Murdock Avenue bridge work over 91 NB & SB

NIGHTTIME LANE CLOSURES:

Sunday through Friday nights from 8:00 PM to 6:00 AM crews will conduct a variety of work with lane closes as noted:

  • I-91 NB & SB (from Exit 17 to Exit 15) for Murdock Avenue Bridge work and paving
  • I-91 SB (on-ramp from Route 15 NB Exit 15) for survey

NIGHTTIME RAMP CLOSURES: Monday night, 10/13, from 9:00 PM to 6:00 AM:

  • I-91 SB (East Main Street to I-91 SB)

NIGHTTIME ROAD CLOSURES:

Sunday through Friday nights from 12:00 AM to 6:00 AM

  • I-91 NB & SB—15-minute closures for bridge work on the Murdock Avenue bridge

NIGHTTIME WORK – BRIDGE DEMOLITION/CONSTRUCTION: Sunday through Thursday nights from 8:00 PM to 6:00 AM

Please read information concerning our nighttime noise monitoring efforts here.

LONG TERM CLOSURES:

  • Murdock Avenue Bridge alternating one-way traffic–Read more on our website here.

 

Girder removal on Murdock Avenue Bridge