Phase 2: Update for the Weeks of November 15 & 22, 2026

HOLIDAY SCHEDULE:

For the week of November 22, there will be no worked scheduled in the project limits from 2:30 PM on Wednesday, November 25 through Monday, November 27 at 6:30 AM. No lane closures are anticipated except in an emergency.

DAYTIME WORK:

Except for the holiday schedule, Monday through Friday from 7:00 AM to 3:30 PM crews will conduct a variety of work as noted throughout the Phase 2 Project limits:

  • Excavate, backfill, formation of subgrade, place aggregate on the following areas:
    • I-691 WB from the I-691 WB bridge over Route 15 and install permanent barrier
    • The Route 15 NB 65B ramp to I-691 WB.
    • Route 15 NB and the I-91 NB median.
  • Work on the Route 15 NB Bridge over I-91 north of East Main Street:
    • Backfill footings and wall of the piers
    • Pour stem and backwall, and set and strip formwork for footings, wingwalls, back walls, pedestals, pier footings, columns, and cap.
    • Install rebar
  • Permanent paving on Route 15 NB 65B ramp to I-691 WB and on Route 15 NB at the Route 15 NB bridge over I-91 north of East Main Street.
  • Work on multiple retaining walls.
  • Remove bituminous wearing surface on the I-691 WB Bridge over Gravel Street
  • Set and strip formwork on the bridge deck of the I-691 WB Bridge over Route 15.
  • Demolish pedestals for the East Main Street Bridge and perform steel repairs.
  • Prep, pour, cure, patch and install penetrating sealer at various locations.
  • Install:
    • Metal beam rail at multiple locations
    • Drainage in the I-91 and Route 15 medians.
    • Signals and traffic foundations on East Main Street.

NIGHTTIME WORK

Except for the holiday schedule, Sunday through Thursday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work. Please read about our night time noise and construction work here.

  • Lane and ramp closures/stoppages on I-91, I-691, and Route 15.
  • Relocate temporary barrier on I-91, I-691, and Route 15 ramps at various locations.
  • Bridge work and sawcutting in various locations
  • Pour bridge deck the Route 15 Bridge over I-91 north of East Main Street
  • Traffic shift at I-691 WB and the Route 15 NB ramp to I-691 WB.
  • Install:
    • Penetration sealer on various bridges
    • Winter epoxy at various locations

NIGHT WORK—Lane Closures:

Except for the holiday schedule, Sunday through Thursday nights from 7:00 PM to 6:00 AM.

  • I-91 NB and SB (Exit 16-18) to clean and blast the East Main Street Bridge and bridge underdecking removal.
  • I-691 WB (Exit 2C to Exit 1A) for temporary barrier relocation.
  • Route 15 SB (Exit 64B to Exit 64A) for bridge underdecking removal and fine grade and pave at the gore of the Exit 65B ramp.
  • I-691 WB (the on-ramp from Preston Avenue to Exit 2A) for traffic shift.

NIGHT WORK—Ramp Closures:  

Except for the holiday schedule, Sunday through Thursday nights from 7:00 PM to 6:00 AM. Detour routes will be in place to guide travelers through the construction.

  • I-91 NB Exit 16 for winter epoxy striping (Sunday 11/15).
  • Route 15 NB Exit 64B for winter epoxy striping (Sunday 11/15 through Tuesday 11/17) and to clean and blast the East Main Street Bridge.
  • Route 15 NB Exit 65B for temporary barrier relocation (Sunday 11/15 through Thursday 11/19) and fine grade and pave at the gore of the Exit 65B ramp
  • Route 66 on-ramp from Preston Avenue for traffic shift (Monday 11/16)
  • Route 66 WB Exit 1A for traffic shift (Monday 11/16)

NIGHTTIME WORK – BRIDGE DEMOLITION/CONSTRUCTION:

LONG-TERM CLOSURES/TRAFFIC PATTERNS:

  • The On-ramp to Route 15 NB, I-91 NB and I-691 EB from East Main Street is closed temporarily for roadway construction and safety. Read more and see detour map by clicking this link.

SAFETY ALERT! ONE WAY; DO NOT ENTER:

Click this link to learn more about not using the off-ramps at East Main Street to enter highways.

Formwork removed on the Route 15 Bridge abutment over I-91 south of East Main Street