DAYTIME WORK:
Monday through Friday from 7:00 AM to 3:30 PM crews will conduct a variety of work as noted throughout the Phase 2 Project limits:
- Excavate, backfill, formation of subgrade, place aggregate on the following areas:
- Route 15 NB and I-91 NB medians.
- Route 15 NB at Paddock Avenue to Route 15 Bridge.
- I-691 WB from the I-691 WB bridge over Route 15 to the I-691 Bridge over Gravel Street.
- I-91 NB, south of East Main Street to the East Main Street Bridge.
- Prep, pour, cure, patch and install penetrating sealer at various locations.
- Set and strip formwork on multiple bridge decks and bridge elements for the Route 15 NB Bridge over I-91 south of East Main Street.
- Form and install rebar on multiple bridges.
- Install:
- Drainage on the Route 15 NB ramp to I-691 WB and in the I-91 and Route 15 medians.
- Illumination both permanent and temporary on I-691.
- Underground signal devices on East Main Street.
- Metal beam rail at various locations on Route 15 NB and I-691 Exit 2A.
- Permanent fencing at various bridges.
- Jacking columns and perform steel repairs at multiple bridges.
NIGHTTIME WORK:
Sunday through Thursday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work. Please read about our night time noise and construction work here.
Lane and ramp closures/stoppages on I-91, I-691, and Route 15.
- Bridge work including containment painting and penetration sealer on multiple bridges.
- Excavate, backfill, formation of subgrade, place aggregate on Route 15 NB from the Route 15 NB ramp to I-91 to the Route 15 NB Bridge over I-91 north of East Main Street.
- Drainage installation on Route 15 NB
- Install overhangs and decking on the Route 15 NB Bridge over I-91 north of East Main Street.
NIGHT WORK—Lane Closures:
Sunday through Thursday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work as noted with the following anticipated closures:
I-91 NB & SB (Exit 16 to Exit 18) for bridge blast and clean, and overhang & decking installation
LONG-TERM CLOSURES/TRAFFIC PATTERNS:
- The On-ramp to Route 15 NB, I-91 NB and I-691 EB from East Main Street is closed temporarily for roadway construction and safety. Read more and see detour map by clicking this link.
SAFETY ALERT! ONE WAY; DO NOT ENTER:
- Click this link to learn more about not using the off-ramps at East Main Street to enter highways.