Phase 3: Update for the Weeks of July 13 & 20, 2026

DAYTIME WORK:

Monday through Friday from 6:00 AM to 2:30 PM crews will conduct a variety of work as noted throughout the Project limits:

  • Sawcut, excavate and backfill in the shoulder of the East Main Street ramp to I-91 SB
  • Sawcut, excavate and backfill I-91 SB median from north end of project limits to Exit 17 for the added lane
  • Set up and maintain water handling
  • Excavate and stockpile streambed channel material at multiple culvert sites
  • Rehabilitate various culverts

NIGHTTIME LANE CLOSURES:

Sunday through Friday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work as noted throughout Project limits:

  • Route 15 SB Exit 64B to Exit 62 for temporary barrier installation
  • I-691 EB from Exit 3 to Exit 1B for temporary barrier installation
  • I-91 SB from Exit 20 to Exit 19 for overhead sign support borings

NIGHTTIME RAMP CLOSURES AND DETOURS:

Closures anticipated from 7:00 PM to 6:00 AM with posted detour routes, weather permitting, as follows:

Workers cutting bituminous concrete behind temporary barrier
Previous Post
I-91 NB Exit 16 to Open in its New Alignment and Exit 17 to Close Permanently on July 16, 2026
Next Post
Phase 3: Detour Route for I-91 SB Exit 17 to East Main Street & Route 15 SB