Phase 2: Update for the Weeks of October 14 and 21, 2024

NIGHT WORK

For the weeks of October 14 and 21, 2024, expect work from 8:00 PM to 6:00 AM (Sunday through Thursday nights).

Lane Closures

  • I-91 NB – Exits 15 to Exit 16 for shoulder excavation and drainage
  • Route 15 NB/SB (Miller Avenue to Paddock Avenue.): to install temporary earth retaining systems
  • I-691 WB (Exit 1A to 2A) for bridge demolition work

Ramp Closures and Detours

Links to the detour routes are on the website:

Sunday through Thursday nights – October 13 through 24, for drainage crossings:

DAY WORK

During weekdays, Monday, October 14 through Friday, October 25, from 6:00 AM to 3:30 PM crews will conduct a variety of work as noted below throughout the I-91, I-691, Route 15 Interchange Phase 2 Project limits:

  • Maintenance and protection of traffic with lane and shoulder closures on I-91, I-691, and Route 15, and some local roads
  • Excavate, backfill, and grade the Route 15 NB Exit 68 W bridge to I-691 WB pier and I-91 median
  • Excavate, backfill, and form subgrade for detention basin area and install detention basin envelope.
  • Install temporary earth retaining system at Route 15 NB Exit 67 off-ramp vicinity and at I-91 NB Exit 16 off-ramp
  • Remove pavement and concrete pavement at:
    • Route 15 NB Exit 68 W off-ramp
    • East Main Street on-ramp to Route 15 NB and I-91 NB and I-691 WB
    • Route 15 NB Exit 68 N-E off-ramp
  • Excavate, backfill, and form subbase for I-91 NB Exit 16
  • Perform wetland creating work; install streambed material
  • Install cofferdam and perform culvert repairs
  • Formwork, form and backfill abutment and wingwall footings for the Route 15 NB bridge to East Main Street
  • Drainage and wetland mitigation work

LONG-TERM CLOSURES/TRAFFIC PATTERNS

Paddock Avenue: One-way alternating traffic controlled by a temporary traffic signal, and nighttime closure/detour on Paddock Avenue over Route 15 between Barr Road and Overlook Road: read more here.

I-91 NB/SB turn-around: Temporary traffic barriers have been installed across the I-91 NB/SB emergency turn-around located just south of the Murdock Avenue overpass. This closure will be I effect until approximately the end of October 2024. Read the alert on our website here.

Previous Post
Phase 1: Update for the Weeks of October 6 and 13, 2024