NIGHT WORK
Anticipated work for this week will be from 8:00 PM to 6:00 AM (Sunday through Thursday nights):
Lane Closures
I-91 NB – Exits 15 to Exit 18 for median widening
I-91 NB – Exits 15 to rest area: installation of temporary barrier
I-91 SB (Exit 18 to 17): bridge demolition
Route 15 NB (Miller Avenue to Paddock Avenue.): Route 15 NB milling, bridge work, traffic shift, and installation of temporary barrier
Route 15 NB (Exit 67 to Exit 68W): Route 15 NB milling and bridge work
I-691 EB (Exit 2A to 1B): milling and paving repairs
I-691 WB (Exit 1A to 2A): bridge demolition and installation of temporary barrier
Ramp Closures and Detours (dates tbd)
Detour routes will be clearly marked:
East Main Street on-ramp to Route 15 NB and I-91 NB and I-691 NB
I-691 EB ramp to Route 15 SB
I-691 WB ramp to I-91 SB
Route 15 NB ramp to I-691 WB
I-91 NB ramp to Route 15 NB (Exit 17)
Route 15 NB Exit 68 N-E off ramp to I-91 NB
DAY WORK
During weekdays, Monday, November 18 through Friday November 22, anticipated work throughout the I-91, I-691, Route 15 Interchange Phase 2 Project limits is summarized below:
Maintenance and protection of traffic with lane and shoulder closures on I-91, I-691, and Route 15, and some local roads.
Excavate, backfill, formation of subgrade, and concrete pavement removal at East Main Street on-ramp to Route 15 NB and I-91 NB and I-691 WB.
Excavate for retaining wall for new Route 15 Exit 67 Bridge to East Main Street and culvert repairs
Backup pavement and prep for traffic shifts on I-91 NB and the Exit 16 vicinity.
Bridge repair work at the I-691 bridges over N. Wall Street.
Bridge back wall and wing wall form work and concrete pour at the Route 15 NB Exit 67 off-ramp bridge vicinity.
Install access for the Route 15 Bridge over 91.
Install new illumination elements.
Install permanent drainage at I-91 NB Exit 16 off ramp.
Install micropiles at Paddock Ave. bridge abutments.
Drill, prep, and test verification pile at the Paddock Avenue Bridge over Route 15.
LONG-TERM CLOSURES/TRAFFIC PATTERNS
Paddock Avenue: one-way alternating traffic controlled by a temporary traffic signal, and nighttime closure/detour on Paddock Avenue over Route 15 between Barr Road and Overlook Road: read more here.
I-91 NB/SB turn-around: Temporary traffic barriers have been installed across the I-91 NB/SB emergency turn-around located just south of the Murdock Avenue overpass. This closure will be I effect until approximately the end of October 2024. Read the alert on our website here.