Phase 1: Update for the Weeks of November 10 & 17, 2024

PLANNED CONSTRUCTION:

November 13 through November 15, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • Stripping overhang brackets installation of waterproof membrane on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
  • Parapet modifications on the I-691 EB bridge over I-91, I-691 EB bridge over Bee Street, and I-691 EB bridge over the ramp from I-691 WB to I-91 SB
  • Shoulder widening and preparation for the installation of permanent barriers on I-91 NB under I-691 EB bridge

November 13, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Backfilling behind the curbing on I-91 NB north of Exit 18

November 17 through November 20, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Adjusting line striping for new stage on southern end of I-91 NB near the Rt 15 NB off-ramp to I-91 NB
  • Epoxy line-striping for winter on the southern end of I-91 NB

November 18 through November 22, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • Stripping overhang brackets installation of waterproof membrane, and forming of the abutment 1 and abutment 2 wall caps on the new bridge on the Exit 1A off-ramp from I-691 E to I-91 NB
  • Fine grading on the I-691 EB off-ramp to I-91 NB

TRAFFIC IMPACTS:

  • Wednesday, November 13, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:
    o I-91 NB double left lane closure from Exit 18 to the rest area
  • Thursday, November 14, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:
    o Traffic shifts on I-91 NB. Traffic will be shifted to the left of the I-91 NB bridge over Bee Street
  • Sunday, November 17, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:
    o I-91 NB double left lane closure from Exit 18 to the rest area
  • Monday, November 18 through Thursday, November 21, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:
    • Traffic shifts on I-91 NB. Traffic will be shifted to the left of the I-91 NB bridge over Bee Street.
    • Closure of the Rt 15 NB off-ramp to I-91 NB

Route 15 NB off-ramp to I-91 NB closure and detour route: