Phase 2: Update for the Week of May 12, 2025

DAY WORK:

During weekdays, Monday, May 12 through Friday, May 16, from 6:00 AM to 3:30 PM crews will conduct a variety of work as noted below throughout the I-91, I-691, Route 15 Interchange Phase 2 Project limits:

  • Maintenance and protection of traffic with lane and shoulder closures on I-91, I-691, and Route 15, and some local roads, as required.
  • Maintain stockpile locations, sweeping, dust control.
  • Excavate and backfill cofferdam and dewater temporary earth retaining for retaining wall on Route 15 NB north of Paddock Avenue Bridge.
  • Install and backfill doublewall blocks and form and pour leveling pads for retaining wall on Route 15 NB north of Paddock Avenue Bridge.
  • Demolition of abutment, wingwalls and footings for the Route 15 NB bridge over I-91.
  • Set and strip formwork for pier footing and stem for the Paddock Avenue Bridge over Route 15.
  • Set and strip formwork for pier footing for the Route 15 bridge over I-91 and pour stem.
  • Bearing pedestal support replacement East Main Street bridge over Route 15 and I-91.
  • Install light bases on I-91.
  • Install wetland plantings.
  • Onsite/offsite trucking.
  • Deliver doublewall blocks.

NIGHTTIME LANE and RAMP CLOSURES:

Closures are possible Sunday through Friday nights from 8:00 PM to 6:00 AM as follows:

NIGHT WORK:

During the Sunday through Friday nights from 7:00 PM to 6:00 AM, crews will conduct a variety of work as noted below throughout Project limits:

  • Shoulder reconstruction on I-91.
  • Concrete pavement removal on Route 15 NB to I-91 NB (Exit 68 NE).
  • Paving for leveling course on I-91 NB.
  • Post-milling line striping.
  • Onsite/offsite trucking.

LONG-TERM CLOSURES/TRAFFIC PATTERNS:

Paddock Avenue: one-way alternating traffic controlled by a temporary traffic signal, and nighttime closure/detour on Paddock Avenue over Route 15 between Barr Road and Overlook Road: read more here.