PLANNED CONSTRUCTION:

October 9 through October 12, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Paving on I-691 EB
  • Paving on I-91 NB
  • Membrane activities on the I-91 NB bridge over Baldwin Avenue
  • Painting safety-markings and post paving striping

October 10 and October 11, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • The following activities on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
    • Forming parapets, backwall and the bridge deck
    • Rebar installation
  • Membrane activities on the I-91 NB bridge over Baldwin Avenue

October 13 through October 17, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Paving on I-91 NB
  • Relocating temporary barriers on I-91 NB
  • Painting safety-markings and post paving striping

October 14 through October 18, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • The following activities on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
    • Forming parapets, backwall and the bridge deck
    • Grading the abutment 1 and abutment 2 approaches
    • Pouring the deck

TRAFFIC IMPACTS:

Wednesday, October 9, and Thursday, October 10, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB right lane closure from Exit 17 to Exit 18
  • I-91 NB double right lane closure from Exit 18 to the rest area
  • I-691 EB right lane closure from Exit 1B to Exit 1

Sunday, October 13, through Tuesday, October 15, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB double left lane closure from Exit 18 to the rest area
  • I-691 EB left lane closure from Exit 1B to Exit 1
  • Closure of the I-691 EB off-ramp to I-91 NB

Wednesday, October 16, and Thursday, October 17, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB right lane closure from Exit 17 to Exit 18
  • I-91 NB double right lane closure from Exit 18 to the rest area
  • Closure of the Route 66 WB off-ramp to I-91 NB
  • Closure of the I-691 EB off-ramp to I-91 NB
  • I-691 EB right lane closure from Exit 1B to Exit 1