Phase 1: Update for the Weeks of October 21 and 28, 2024

October 24, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Paving on I-91 NB
  • Post paving line striping I-91 NB

October 25, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • The following activities on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
    • Forming the parapets
    • Pouring the southern parapet
  • Filling abutment 1 on the I-691 EB off-ramp to I-91 NB

October 27 through October 31, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Relocating temporary barriers on I-91 NB
  • Traffic shift on I-91 NB
  • Sawcutting activities on the I-691 EB off-ramp to I-91 NB

 

October 28 through November 1, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • The following activities on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
    • Forming parapets
    • Pouring the northern parapet on the I-691 EB off-ramp to I-91 NB
  • Drainage activities on the left side of I-691 EB

TRAFFIC IMPACTS:

Thursday, October 24, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

Sunday, October 27, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

Closure and Detour Maps: