Phase 1: Update for the Weeks of November 24, December 1, and December 8, 2024

THANKSGIVING HOLIDAY

No work is anticipated on the project over the holiday from 6:00 AM on Wednesday, November 27 to 8:00 PM on Friday, November 29. No closures are scheduled except for emergency.

December 2 to December 6, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • Forming for parapet modifications on the I-691 EB bridge over Bee Street
  • Removing asphalt and concrete on the I-691 EB off-ramp to I-91 NB

December 2 to December 5, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Prepping the I-691 EB off-ramp to I-91 NB and the Route 66 WB off-ramp to I-91 NB for a traffic shift
  • Epoxy line-striping for winter on I-91 NB
  • Line striping for the traffic shift on the I-691 EB off-ramp to I-91 NB and the Route 66 WB off-ramp to I-91 NB

December 9 to December 13, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • Forming for the parapet modifications on the I-691 EB bridge over I-91 and the I-691 EB bridge over Bee Street
  • Full depth roadway reconstruction including drainage infrastructure of the I-691 EB off-ramp to I-91 NB

TRAFFIC IMPACTS:

Monday, December 2 through Thursday, December 5, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures: