Phase 1: Update for the Weeks of March 30 & April 6, 2025

March 27 to March 29, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:

  • Installation of keeper blocks on the I-91 NB bridge over Baldwin Avenue
  • Filling and grading abutment one on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB and the I-691 EB off-ramp to I-91 NB
  • Priming and blasting the I-691 EB bridge over I-91 and I-691 EB bridge over the ramp from I-691 WB to I-91 SB
  • Grading and placing stones on the slope and drilling, setting, and pouring the noise wall posts installation along the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB

April 1 to April 5, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:

  • Installing the noise wall posts on the I-91 NB bridge over Bee Street
  • Installation of keeper blocks on I-691 EB bridge and the I-91 NB bridge over Bee Street
  • Priming and blasting the I-691 EB bridge over I-91 and I-691 EB bridge over the ramp from I-691 WB to I-91 SB
  • Grading and placing stones on the slope and drilling, setting, and pouring the noise wall posts installation along the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB

April 8 to April 12, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:

  • Setting the noise wall posts installations along the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB
  • Forming and pouring the barriers on the I-91 NB bridge over Bee Street
  • Building the snow shelf and relocating barriers on the I-691 EB off-ramp to I-91 NB
  • Paving the I-691 EB off-ramp to I-91 NB

TRAFFIC IMPACTS:

There are no anticipated traffic impacts from Thursday, March 27 to Saturday, April 12.  