March 27 to March 29, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:
- Installation of keeper blocks on the I-91 NB bridge over Baldwin Avenue
- Filling and grading abutment one on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB and the I-691 EB off-ramp to I-91 NB
- Priming and blasting the I-691 EB bridge over I-91 and I-691 EB bridge over the ramp from I-691 WB to I-91 SB
- Grading and placing stones on the slope and drilling, setting, and pouring the noise wall posts installation along the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB
April 1 to April 5, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:
- Installing the noise wall posts on the I-91 NB bridge over Bee Street
- Installation of keeper blocks on I-691 EB bridge and the I-91 NB bridge over Bee Street
- Priming and blasting the I-691 EB bridge over I-91 and I-691 EB bridge over the ramp from I-691 WB to I-91 SB
- Grading and placing stones on the slope and drilling, setting, and pouring the noise wall posts installation along the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB
April 8 to April 12, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:
- Setting the noise wall posts installations along the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB
- Forming and pouring the barriers on the I-91 NB bridge over Bee Street
- Building the snow shelf and relocating barriers on the I-691 EB off-ramp to I-91 NB
- Paving the I-691 EB off-ramp to I-91 NB
TRAFFIC IMPACTS:
There are no anticipated traffic impacts from Thursday, March 27 to Saturday, April 12.