February 20 and February 21, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Drainage activities on the I-691 EB off-ramp to I-91 NB
- Parapet modifications and replacing the steel bearings on the I-691 EB bridge over I-91
- Demolition of the existing bridge on the exit ramp from I-691 EB over I-91 NB
- Grading and filling the slope on abutment 1 on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
- Drilling, setting, and pouring for the noise wall posts installation from the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB
February 24 to February 28, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:
- Parapet modifications on the I-691 EB bridge over I-91
- Grading and filling the slope on abutment 2 on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
- Replacing the steel bearings on the I-691 EB bridge over I-91
- De-leading the I-691 EB bridge over I-91 and the I-691 EB bridge over the ramp from I-691 WB to I-91 SB
- Drilling, setting, and pouring for the noise wall posts installation from the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB
March 3 to March 7, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:
- Parapet modifications on the I-691 EB bridge over I-91
- Grading and filling the slope on abutment 2 on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
- Replacing the steel bearings on the I-691 EB bridge over I-91
- De-leading the I-691 EB bridge over I-91 and I-691 EB bridge over the ramp from I-691 WB to I-91 SB
- Drilling, setting, and pouring for the noise wall posts installation from the Rt 15 NB off-ramp to I-91 NB and along I-91 NB to the I-91 NB off-ramp to Rt 66 EB