Construction Alerts
Update: Weeks of March 4 & 11, 2024
From March 4 through March 15, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities: Building the sound…
Update: Week of February 26, 2024
From February 26 through March 1, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities: Building the sound…
Update: Weeks of February 12 & 19
From February 12 through February 16, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities: Backfilling the footings…
Update: Weeks of January 24 & February 5
PLANNED CONSTRUCTION: From January 24 through January 28, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities: Repairing…
Update: January 5 – 15, 2024
There will be no planned construction activities or traffic impacts on the project from Friday, January 5, through Friday, January 15, 2024.
Update: December 22, 2023 – January 5, 2024
There will be no planned construction activities or traffic impacts from Friday, December 22, 2023, to Friday, January 5, 2024. Below – recent…
Update: December 5 – December 22
PLANNED CONSTRUCTION: From December 5 through December 22, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities: Widening…
Update: Weeks of Nov. 19, 23, & 27, 2023
PLANNED CONSTRUCTION: Lane Closures possible Sunday 11/19 through Tuesday 11/21 between 7:00 PM and 6:00 AM as follows: CT Route 66 EB (Ramp 9N…
Update for the Weeks of Nov. 5 and Nov. 12, 2023
Lane Closures possible Sunday 11/5 through Wednesday 11/15 between 7:00 PM and 6:00 AM as follows (except no lane closures are anticipated Thursdays, Fridays,…