HOLIDAY SCHEDULE:
For the week of November 22, there will be no work scheduled in the project limits from 2:30 PM on Wednesday, November 25 through Monday, November 27 at 6:30 AM. No lane closures are anticipated except in an emergency. ALSO, there will be no nightwork from Wednesday through Saturday nights, November 25 through 29.
DAYTIME WORK:
Except for the holiday schedule, Monday through Friday from 7:00 AM to 3:30 PM crews will conduct a variety of work as noted throughout the Phase 3 Project limits:
- Maintain water handling at multiple sites of culvert rehabilitation.
- Set parapets, formwork formation/reinforce and pour moment slab for the retaining wall on Route 15 SB just north of the East Main Street Bridge.
- Culvert rehabilitation at multiple sites.
- Sawcut, excavate, and backfill in the I-91 SB median at the Paddock Avenue Bridge vicinity, shaping swales and slopes from Broad Street to the I-691 EB Bridge over Route 15.
- Sawcut, excavate, and backfill in the I-91 SB right shoulder widening and underdrain installation.
- Grade and set permanent median barrier.
- Excavate for and install support of excavation, and partial demolition of the Route 15 SB ramp bridge to I-91 SB over the I-91 SB ramp to Route 15 SB.
- Backfill and install rebar for Murdock Avenue pier footing.
- Construction staking sitewide.
- Clearing and grubbing on the Route 15 SB ramp to I-91 SB and sitewide.
- Formwork formation/reinforce and pour pier footing on the Murdock Avenue Bridge over I-91.
- Joint repairs at multiple bridges and sealing culverts.
- Install drainage in Route 15 SB median near Miller Avenue.
- Install drainage ramp at the East Main Street on-ramp to I-91 SB.
- Relocate water mains and sewer main (bypass pump) under the East Main St. Bridge over I-91.
- Deliver permanent median barrier on Route 15 SB.
*NIGHTTIME WORK:
Except for the holiday schedule, Sunday through Friday nights from 7:00 PM to 6:00 AM
- Miscellaneous maintenance and protection of traffic, signage, and winter preparation work.
- Install temporary traffic barrier for work on access road to Route 66.
- Create access windows for CTDOT maintenance.
- Epoxy line striping sitewide.
*NIGHTTIME LANE & RAMP CLOSURES:
Except for the holiday schedule, Sunday through Friday nights from 8:00 PM to 6:00 AM
- I-91 SB (from Exit 17 to Exit 15) for paving.
- Route 66 WB (Lane closure) from the on-ramp from Preston Avenue to Exit 1B.
- Route 66 WB (Ramp closure) Exit 1A – Route 66 WB to I-91 NB (a detour route will be in place).
ROAD CLOSURES: Murdock Avenue on November 16 and 17 from 9:00 PM to 6:00 AM for curb removal. Detour route signs will be in place.
NIGHTTIME WORK – BRIDGE DEMOLITION/CONSTRUCTION: Sunday through Thursday nights from 8:00 PM to 6:00 AM – Please read information concerning our nighttime noise monitoring efforts here.
LONG TERM CLOSURES: Murdock Avenue Bridge alternating one-way traffic–Read more on our website here.
*Schedule is subject to change due to weather and other circumstances.