HOLIDAY SCHEDULE: There will be no work on the project from Thursday, July 2 from 2:30 PM through Monday, July 6 at 6:00 AM in honor of the Fourth of July national holiday.
DAYTIME WORK: Aside from the holiday schedule, Monday through Friday from 6:00 AM to 2:30 PM crews will conduct a variety of work as noted throughout the Phase 3 Project limits:
- Excavate and place gravel in the I-91 SB median from north end of project limits to Exit 17 for the added lane
- Rehabilitate various culverts
- Relocate utility cables on Murdock Avenue
- Install bypass cable along I-91 SB south of Exit 17
NIGHTTIME LANE CLOSURES: Sunday through Friday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work as noted throughout the Phase 3 Project limits:
- Route 15 SB from the on-ramp from I-691 EB to Route 15 SB Exit 62 for temporary widening and traffic shift
- I-691 EB from Exit 3 to Exit 1B for paving operations
NIGHTTIME RAMP CLOSURES AND DETOURS: Closures anticipated from 7:00 PM to 6:00 AM with posted detour routes, weather permitting, as follows:
- I-691 EB: Broad Street on-ramp to I-691 EB (Monday, 6/29 and Tuesday, 7/7) for paving and traffic shift
- I-691 EB Exit 1B: I-691 EB ramp to Route 15 SB (Monday, 6/29 and Tuesday, 7/7) for paving and traffic shift
- Route 15 SB: On ramp from East Main Street to Route 15 SB (Wednesday 7/8) for traffic shift
- I-91 SB Exit 17: The ramp from I-91 SB to East Main Street (Wednesday 7/8) for traffic shift
- Route 15 SB Exit 63A: The ramp from Route 15 SB to I-91 SB (Wednesday 7/8) for traffic shift