Phase 1: Update for the Weeks of April 13 and 20, 2025

Notice: Beginning on Monday, April 14, the emergency turnaround on I-91 NB near the Rest Area and north of Exit 19 on I-91 SB, will be closed for two weeks.

April 13 to April 17, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Priming and blasting of the I-691 EB bridge over I-91 and the I-691 EB bridge over the ramp from I-691 WB to I-91 SB
  • Milling of the I-91 NB bridge over Bee Street and I-91 NB north of the I-91 NB bridge over Baldwin Avenue

April 14 to April 18, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:

  • Excavation activities at I-91 NB bridge over Bee Street
  • Installing the sound barrier wall panels and finishing the slopes on I-691 EB and I-91 NB
  • Fine grading and paving on the I-691 EB off-ramp to I-91 NB
  • Forming and pouring the transition barrier on the I-91 NB bridge over Bee Street
  • Priming and blasting the I-691 EB bridge over the ramp from I-691 WB to I-91 SB and the I-691 EB bridge over I-91
  • Installing lighting along the sound barrier wall on I-691 EB and I-91 NB

April 16 to April 17, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Milling the I-91 NB bridge over Bee Street and the I-91 NB bridge over Baldwin Avenue

April 21 to April 25, during daytime hours, from 7:00 AM to 3:30 PM, crews will continue the following activities:

  • Excavation activities at I-91 NB bridge over Bee Street
  • Installing the sound barrier wall panels and finishing the slopes on I-691 EB and I-91 NB
  • Installing lighting along the sound barrier wall on I-691 EB and I-91 NB
  • Full depth reconstruction of the I-91 NB turnaround
  • Installing metal beam rail on the I-691 EB off-ramp to I-91 NB and the I-91 NB ramp to Route 66 WB

April 21 to April 24, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Full depth concrete patches on I-691 EB
  • Priming and blasting of bridges the I-691 EB bridge over I-91 and the I-691 EB bridge over the the ramp form I-691 WB to I-91 SB
  • Milling bridge the I-91 NB bridge over Bee Street and I-91 NB north of bridge the I-91 NB bridge over Baldwin Ave.
  • Priming and blasting the I-691 EB bridge over the ramp from I-691 WB to I-91 SB and the I-691 EB bridge over I-91

April 21 to April 22, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Milling on the I-91 NB bridge over Bee Street and the I-91 NB bridge over Baldwin Avenue

April 21 to April 23, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Moving the temporary barrier on I-91 NB

April 22 to April 24, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Backing up the pavement and building the shelf on I-91 NB and Route 66 WB

April 24, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Removing the cable rail on Route 66 EB

TRAFFIC IMPACTS:

Sunday, April 13, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB right lane closure from Exit 17 to Exit 19
  • I-91 NB double right lane closure from Exit 18 to Exit 19
  • Closure of the Route 15 NB off-ramp to I-91 NB

Monday, April 14, through Wednesday, April 16, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB right lane closure from Exit 17 to Exit 19
  • I-91 NB double right lane closure from Exit 18 to Exit 19
  • I-91 NB left lane closure from Exit 17 to Exit 19
  • I-91 NB double left lane closure from Exit 18 to Exit 19
  • Closure of the Route 15 NB Exit 68 W to I-691 WB and I-91 NB