From February 12 through February 16, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Backfilling the footings and wingwalls on the I-91 NB bridge over Baldwin Avenue
- Filling of the embankment at Exit 1A for the future bridge from I-691 EB to I-91 NB
- Constructing a temporary illumination ramp for I-91 NB to Route 66 EB
From February 19 to February 23, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Build sound barrier wall embankment along the I-91 NB and Exit ramp to Route 66 EB
- Drainage of the Route 66 WB off ramp to I-91 NB
- I-691 EB parapet modification and endblocks
- I-91 NB widening north of the I-91 NB bridge over Baldwin Ave.
- Full depth reconstruction on the I-91 NB Exit ramp to Route 66 EB
- Damp-proofing the I-91 NB bridge over Baldwin Avenue
TRAFFIC IMPACTS:
There will be no planned detours from Wednesday, February 14 to February 23, 2024.