Planned Construction Activities

NIGHT WORK

  • Paddock Avenue Utility Work 9:00 PM to 6:00 AM.
  • Lane Closures 8:00 PM to 6:00 AM
    • Route 15 NB – From Miller Ave. to Exit 68 N-E – for drill and pin temporary barrier

DAY WORK

NOTICE: Paddock Avenue Day Work – Frontier Utilities will have a heavy presence on Paddock Avenue moving cables from 8:30 AM to 4 PM. During this time there will be alternating one-way traffic with Meriden Police control.

During weekdays, Monday, June 3 through Friday, June 14, from 6:00 AM to 3:30 PM crews will conduct a variety of work as noted below on throughout the I-91, I-691, Route 15 Interchange Phase 2 Project limits:

  • Maintenance and protection of traffic with lane and shoulder closures on I-91, I-691, and Route 15, and some local roads
  • Form subgrade for temporary ramp widening at Route 15 NB Exit 69 N-E ramp
  • Sawcut, excavate, backfill for insertion valve in Paddock Avenue
  • Installation of temporary poles and wiring at Paddock Avenue.
  • Installation of erosion and sedimentation controls
  • Grubbing Excavation
  • Chipping and clearing in I-691 EB/WB gore area
  • Survey
  • Installation/removal of metal beam rail
  • Install temporary illumination on Route 15 NB and ramps
  • Utility work on Paddock Avenue