From May 13 through May 23, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:

  • On the I-91 NB bridge over Baldwin Avenue:
    • Install wingwall parapets
    • Pour wingwall parapets
  • Drainage work and grading activities on I-691 EB
  • Partial depth patching on the I-691 EB bridge over I-91
  • Paving of I-91 NB left lane (behind the concrete barrier)
  • Fine grading of topsoil on Route 66 WB off ramp to I-91 NB

From May 13 through May 17, during nighttime hours, from 8:30 PM to 6:00 AM, crews will conduct the following activities:

  • Milling and paving on I-91 NB and I-691 EB
  • Temporary barrier relocation and installation on I-91 NB
  • I-91 NB traffic shift to the left from Exit 18 to the bridge over Baldwin Avenue
  • Installation of the deck membrane on the I-91 NB bridge over Baldwin Avenue
  • Safety markings after milling on I-91 NB
  • Safety markings for traffic shift on I-91 NB

TRAFFIC IMPACTS:

On Monday, May 13, during nighttime hours, motorists should expect the following traffic impacts and closures:

  • I-91 NB left lane closure near Exit 18, from 8:00 PM to 10 AM
  • I-91 NB double left and right lane closure near Exit 18, from 10 PM to 2 AM
  • Closure of the Route 66 EB off ramp to I-91 NB, from 10 PM to 6 AM (see detour graphic below)
  • Closure of Route 66 WB off ramp to I-91 NB, from 10 PM to 6 AM (see detour graphic below)

On Tuesday, May 14, during nighttime hours, motorists should expect the following traffic impacts and closures:

  • I-91 NB left lane closure near Exit 18, from 8:00 PM to 10 AM
  • I-91 NB double left and right lane closure near Exit 18, from 10 PM to 2 AM
  • From Wednesday, May 15 to Friday, May 17, during nighttime hours, motorists should expect the following traffic impacts and closures:
  • I-91 NB left lane closure near Exit 18, from 8:00 PM to 10 AM
  • I-91 NB double left and right lane closure near Exit 18, from 10 PM to 2 AM
  • Closure of the Route 66 EB off ramp to I-91 NB, from 10 PM to 6 AM (see detour graphic below)
  • Closure of Route 66 WB off ramp to I-91 NB, from 10 PM to 6 AM (see detour graphic below)

The closure of the Route 66 EB off ramp to I-91 NB will detour traffic to Exit 1 to Preston Avenue, back to I-91 NB.

The closure of the Route 66 WB off ramp to I-91 NB will detour traffic to Exit 1B to I-91 SB, to Exit 17 to Route 15 SB, take a left onto East Main Street, and back onto I-91 NB.

 