On July 3, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:

  • Full depth reconstruction of the Route 66 WB off-ramp to I-91 NB
  • Full depth construction of the following ramps:
    • I-691 EB off-ramp to I-91 NB and Preston Ave on-ramp to I-91 NB
    • Preston Ave on-ramp to the I-91 NB off-ramp to the rest area
  • Drainage of the Route 66 WB off-ramp to I-91 NB
  • Building two bridge abutments on the exit ramp from I-691 EB to I-91 NB
  • Utility relocations on I-91 NB

Crews will be out of the project area by 3:00 PM on Wednesday, July 3, and will return on Sunday, July 7, at 8:30 PM.

From July 7 through July 11, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Sawcutting, drilling and plugging activities on I-91 NB
  • Sawcutting activities on I-91 NB and I-691 EB roadway concrete repairs
  • Pulling slabs on I-91 NB
  • Partial depth repairs on the following bridges:
    • I-691 EB bridge over I-91
    • I-691 EB bridge over Bee Street
    • I-691 EB bridge over the ramp from I-691 WB to I-91 SB

From July 8 through July 12, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:

  • Full depth reconstruction of the Route 66 WB off-ramp to I-91 NB
  • Full depth construction of the following ramps:
    • I-691 EB off-ramp to I-91 NB and Preston Ave on-ramp to I-91 NB
    • Preston Ave on-ramp to the I-91 NB off-ramp to the rest area
  • Building two bridge abutments on the exit ramp from I-691 EB to I-91 NB
  • Utility relocations on I-91 NB

TRAFFIC IMPACTS:

  • On Tuesday, July 2, during nighttime hours, motorists should expect the following traffic impacts and closures:
    • I-91 NB right lane closure near Exit 18 to the rest area, from 8 PM to 10 PM
    • I-91 NB double right lane closure from Exit 18 to the rest area, from 10 PM to 6 AM
  • From Sunday, July 7, through Thursday, July 11, during nighttime hours, motorists should expect the following traffic impacts and closures:
    • I-91 NB right lane closure from Exit 18 to the rest area, from 8 PM to 10 PM
    • I-91 NB double right lane closure from Exit 18 to the rest area, from 10 PM to 6 AM
    • I-691 EB left lane closure from Exit 1B to Exit 1, from 8 PM to 6 pour