From March 18 through March 22, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:

  • Continue building of the sound barrier wall embankment along I-91 NB off ramp to Route 66 EB
  • Drainage activities around the future sound barrier wall site
  • Removal of asphalt and roadway grading near the sound barrier wall site
  • I-691 EB parapet modifications
  • Partial milling and paving of left lane on I-691 EB
  • I-91 NB widening and drainage activities north of the I-91 NB bridge over Baldwin Avenue
  • Various types of bridge work activities at the I-91 NB bridge over Baldwin Avenue

From March 25 through March 29, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:

  • Building of the sound barrier wall embankment along I-91 NB off ramp to Route 66 EB
  • Drainage activities around the future sound barrier wall site
  • Removal of asphalt and roadway grading near the sound barrier wall site
  • I-691 EB parapet modifications
  • Paving of I-691 EB
  • I-91 NB widening and drainage activities north of the I-91 NB bridge over Baldwin Avenue
  • Partial deck patching of the following bridges:
    • I-691 EB bridge over I-91
    • I-691 EB bridge over Bee Street
    • I-691 EB bridge over ramp from I-691 WB to I-91 SB

TRAFFIC IMPACTS:

  • From March 18 to March 29, during daytime hours, from 7:00 AM to 3:00 PM, there will be occasional lane closures on I-691 EB.
  • There will be no planned detours from March 18 to March 29.

 