From April 16 through April 19, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:
- Removal of asphalt and roadway grading along I-91 NB off ramp to Route 66 EB
- Drainage activities on I-691 EB
- Partial depth patching on the I-691 EB bridge over I-91
- Drainage work and fine grading activities on I-91 NB
- Installation of overhang brackets, form parapets, deck pans, and shear studs on the I-91 NB bridge over Baldwin Avenue
From April 22 through April 26, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:
- Drainage activities, grading and paving preparation on I-691 EB
- Deck forms for bridge deck concrete pour of the I-91 NB over Baldwin Avenue
- Removal of the drainage system for the bridge on the exit 1A ramp from I-691 EB to I-91 NB
- Partial depth patching of decks on I-691 EB
- Fine grading and drainage activities at the median on I-91 NB
- Fine grading activities on the Route 66 WB off ramp to I-91 NB
- Continue to install shear studs on the I-91 NB bridge over Baldwin Avenue
TRAFFIC IMPACTS:
There will be no planned detours or traffic impacts from April 16 to April 26.