From March 4 through March 15, during daytime hours, from 7:00 AM to 3:00 PM, crews will conduct the following activities:

  • Building the sound barrier wall embankment along I-91 NB off ramp to Route 66 EB
  • Drainage work in the sound barrier wall embankment area
  • I-691 EB parapet modifications and endblocks
  • Widening of I-91 NB north of the I-91 NB bridge over Baldwin Avenue
  • Full depth reconstruction of the I-91 NB ramp to Route 66 EB
  • Bridge demolition on the I-91 NB bridge over Baldwin Ave.
  • Partial deck patching on I-691 bridges over:
    • Bee Street
    • I-91
    • The I-691 EB bridge over the ramp from I-691 WB to 91 SB
  • Installing ramp illumination along Route 66 WB off ramp to I-91 NB
  • Surveying project -wide

There will be no planned detours from Monday, March 4 to Sunday. March 17, 2024.

 

Parapet demolition on the I-91 NB bridge over Baldwin Avenue.
Parapet demolition on the I-91 NB bridge over Baldwin Avenue.
Next Post
Program Phase 2: Start Work March 4, 2024