PLANNED CONSTRUCTION:
From January 24 through January 28, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Repairing potholes on I-91 NB and I-691 EB
- Pouring of concrete for abutment 1 & 2 on the I-91 NB bridge over Baldwin Avenue
- Milling of I-691 EB and the I-691 EB off ramp to I-91 NB
The week of January 28 through February 3, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Demolition of bridge membrane and sound decks on the I-691 EB bridges over:
- I-91
- Bee Street
- The ramp from I-691 WB (Route 66) to I-91 SB
- Installation of south backwalls and wingwalls for the I-91 NB bridge over Baldwin Avenue
- Filling to grade of the Route 66 WB (I-691 WB) off ramp to I-91 NB and the bridge on the Exit ramp from I-691 EB over I-91 NB (I-691 EB Exit 1A)
- Stripping the topsoil, boxout and place process material for the widening of I-91 NB (north of the I-91 NB bridge over Baldwin Avenue)
The week of February 5 through February 9, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Continue the installation of south backwalls and wingwalls for the I-91 NB bridge over Baldwin Avenue
- Continue filling to grade the Route 66 WB Exit 1A ramp – (Route 66 WB [I-691 WB] off ramp to I-91 NB) and the I-691 EB Exit 1A bridge on the Exit ramp from I-691 EB over I-91 NB
- Continue stripping the topsoil, boxout and place process material for the widening of I-91 NB (north of the I-91 NB bridge over Baldwin Avenue)
- Partial deck patching on the I-691 EB bridges over:
- I-91
- Bee Street
- The ramp from I-691 WB (Route 66) to I-91 SB
- Install a silt fence, and clearing materials and stripping the topsoil in the soundwall area
- Demolition of the first span on the I-691 EB Exit 1A bridge on Exit ramp from I-691 EB over I-91 NB
DETOURS
There will be no planned detours from Wednesday, January 24 to Friday, February 9, 2024.