DAYTIME WORK:
Monday through Friday from 7:00 AM to 3:30 PM crews will conduct a variety of work as noted throughout the Phase 3 Project limits:
- Maintain water handling at multiple sites of culvert rehabilitation
- Culvert rehabilitation at multiple sites
- Haul in stockpile supplemental streambed material and install at required sites
- Install drainage and retaining wall along Route 15 SB in the vicinity of the on-ramp from I-91 SB
- Sawcut, excavate and backfill in the I-91 SB median from north end of project limits to Exit 17 for the added lane
- Sawcut, excavate and backfill in the I-91 SB right shoulder and Route 15 SB median
- Excavate for and install support of excavation and partial demolition of the Route 15 SB ramp bridge to I-91 SB over the I-91 SB ramp to Route 15 SB
- Construction staking sitewide
- Install parapet caps, curb, deck ends at the I-691 EB Bridge over Gravel Street
- Joint repairs and sealing culverts at multiple bridges
- Install drainage in Route 15 SB median near Paddock Avenue
- Install drainage on I-91 SB median north end at the East Main Street ramp to I-91 SB
*DAYTIME LANE CLOSURES:
Sunday through Thursday from 8:00 AM to 2:00 PM:
- I-91 SB lane closures (Murdock Avenue to Exit 15) for shoulder reconstruction
NIGHTTIME WORK:
Sunday through Friday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work as noted:
- Mastic repairs on Route 15 NB south of Miller Avenue
- Chip haunches on the I-691 WB bridge over I-91
- Removal of existing masonry for wall and parapet on the I-691 EB Bridge over Gravel Street
- Pave I-91 SB median shoulder from Murdock Avenue to the south end of the project limits
- Pave I-691 EB median shoulder
- Stage 1 demolition and removal of water line on the Murdock Avenue bridge over 91 NB & SB
- Maintenance of existing illumination
- Line striping on I-91 SB
*NIGHTTIME LANE CLOSURES:
Sunday through Friday nights from 8:00 PM to 6:00 AM crews will conduct a variety of work with lane closes as noted:
- I-91 SB (from Exit 17 to Exit 15) for median replacement work and sawcutting
- Route 15 NB south of Miller Avenue for mastic work
NIGHTTIME WORK – BRIDGE DEMOLITION/CONSTRUCTION:
Sunday through Thursday nights from 8:00 PM to 6:00 AM – Please read information concerning our nighttime noise monitoring efforts here.
LONG TERM CLOSURES:
- Murdock Avenue Bridge alternating one-way traffic–Read more on our website here.
*Schedule is subject to change due to weather and other circumstances; see website for updates to this schedule.
Check out the recent drone shots of Phase 3 of the project here.