Phase 3: Update for the Weeks of June 15 and 22, 2026

DAYTIME WORK: Monday through Friday from 6:00 AM to 2:30 PM crews will conduct a variety of work as noted throughout the I-91, I-691, Route 15 Interchange Phase 3 Project limits:

  • Construction of project limit access at various location
  • Construction staking
  • Sawcutting and removal of asphalt pavement on I-91 SB between the Route 15 NB Bridge over I-91 (south of East Main Street) and Murdock Avenue
  • Sawcut, excavate and backfill the I-91 SB median from north end of project limits to Exit 17

NIGHTTIME LANE CLOSURES: Sunday through Friday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work as noted throughout the I-91, I-691, Route 15 Interchange Phase 3 Project limits:

  • I-691 EB from Exit 3 to Exit 1B for milling and paving operations
  • Route 15 SB from Exit 64A to Miller Avenue for milling and paving operations

NIGHTTIME RAMP CLOSURES AND DETOURS: Closures anticipated from 7:00 PM to 6:00 AM Tuesday night 6/16, Sunday night 6/21, and Monday night, 6/22), weather permitting.
Detour routes will be posted:

Milling on I-691 EB