Phase 1: Update for the Weeks of September 8 and 15, 2024

PLANNED CONSTRUCTION:

September 10 through September 12, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Relocating the temporary barrier on I-91 NB
  • Installing safety markings on I-691 EB

September 10 through September 13, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • Building forms for the backwall on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
  • Grading the roadway swales and slopes along I-91 NB

September 15 through September 19, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:

  • Milling activities on I-91 NB
  • Steel installation on the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB

September 16 through September 20, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:

  • On the new bridge on the Exit 1A off-ramp from I-691 EB to I-91 NB
  • Grading the approaches
  • Installing the overhang brackets
  • Installing sign foundations

TRAFFIC IMPACTS:

Tuesday, September 10, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-691 EB right lane closure from Exit 1B to Exit 1
  • I-691 EB left lane closure from Exit 1B to Exit 1 (8 PM to 12 AM)
  • Closure of the I-691 EB off-ramp to I-91 NB (12 AM to 6 AM)
  • Closure of the Route 66 WB off-ramp to I-91 NB (12 AM to 6 AM)
  • I-91 NB right lane closure from Exit 17 to Exit 18
  • I-91 NB double right lane closure from Exit 18 to the rest area

Wednesday, September 11, and Thursday, September 12, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB right lane closure from Exit 17 to Exit 18
  • I-91 NB double right lane closure from Exit 18 to the rest area

Sunday, September 15, through Tuesday, September 17, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB double left lane closure from Exit 16 to the rest area

Wednesday, September 18, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB left lane closure from Exit 17 to Exit 18
  • I-91 NB right lane closure from Exit 17 to Exit 18
  • Closure of the I-691 EB off-ramp to I-91 NB (12 AM to 6 AM)
  • Closure of the Route 66 WB off-ramp to I-91 NB (12 AM to 6 AM)

Thursday, September 19, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • I-91 NB right lane closure from Exit 17 to Exit 18
  • I-91 NB double right lane closure from Exit 18 to the rest area
  • Closure of I-691 EB off-ramp to I-91 NB (12 AM to 6 AM)
  • Route 66 WB right lane closure from the Preston Avenue on-ramp to the I-691 WB off-ramp to I-91 SB
  • Closure of the Route 66 WB off-ramp to I-91 NB
  • 15-minute road closures on I-691 WB (12 AM to 5 AM)

Friday, September 20, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:

  • Route 66 WB right lane closure from the Preston Avenue on-ramp to the I-691 WB off-ramp to I-91 SB
  • Closure of the Route 66 WB off-ramp to I-91 NB
  • 15-minute road closures on I-691 WB (12 AM to 5 AM)
  • Route 66 WB left lane closure from the Preston Avenue on-ramp to the I-691 WB off-ramp to I-91 SB
Next Post
Paddock Ave/Overlook Road Intersection NO TURN ON RED and Traffic Signal
Previous Post
Alternating One-Way Traffic on Paddock Avenue Begins September 15, 2024