Planned Construction Activities
NIGHT WORK
- Paddock Avenue Utility Work 9:00 PM to 6:00 AM.
- Lane Closures 8:00 PM to 6:00 AM
- Route 15 NB – From Miller Ave. to Exit 68 N-E – for drill and pin temporary barrier
DAY WORK
NOTICE: Paddock Avenue Day Work – Frontier Utilities will have a heavy presence on Paddock Avenue moving cables from 8:30 AM to 4 PM. During this time there will be alternating one-way traffic with Meriden Police control.
During weekdays, Monday, June 3 through Friday, June 14, from 6:00 AM to 3:30 PM crews will conduct a variety of work as noted below on throughout the I-91, I-691, Route 15 Interchange Phase 2 Project limits:
- Maintenance and protection of traffic with lane and shoulder closures on I-91, I-691, and Route 15, and some local roads
- Form subgrade for temporary ramp widening at Route 15 NB Exit 69 N-E ramp
- Sawcut, excavate, backfill for insertion valve in Paddock Avenue
- Installation of temporary poles and wiring at Paddock Avenue.
- Installation of erosion and sedimentation controls
- Grubbing Excavation
- Chipping and clearing in I-691 EB/WB gore area
- Survey
- Installation/removal of metal beam rail
- Install temporary illumination on Route 15 NB and ramps
- Utility work on Paddock Avenue