August 11 through August 15, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:
- Full depth repairs on I-691 EB
August 12 through August 16, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Full depth construction and drainage activities on the Route 66 WB off-ramp to I-91 NB
- Fine grading of the off-ramp from I-91 NB to Route 66 EB and ramp from Route 66 EB to I-91NB
- Swale grading on ramps from I-91 NB to Route 66 EB and ramp from Route 66 EB to I-91NB
- Forming and pouring of the wall caps for the bridge on the Exit 1A ramp from I-691 EB over I-91 NB
August 18 through August 22, during nighttime hours, from 8:30 PM to 6:30 AM, crews will conduct the following activities:
- Full depth repairs on I-691 EB
August 19 through August 23, during daytime hours, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
- Full depth construction and drainage activities on the Route 66 WB off-ramp to I-91 NB
- Fine grading of the off-ramp from I-91 NB to Route 66 EB and ramp from Route 66 EB to I-91NB
- Swale grading on ramps from I-91 NB to Route 66 EB and ramp from Route 66 EB to I-91NB
- Stripping of the caps and building the form for abutment 2 on the bridge on the Exit 1A ramp from I-691 EB over I-91 NB.
TRAFFIC IMPACTS:
Sunday, August 11, through Thursday, August 15, during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:
- I-691 EB right lane closure from Exit 1B to Exit 1
- I-691 EB left lane closure from Exit 1B to Exit 1
Sunday, August 18, through Thursday, August 22, between during nighttime hours from 8 PM to 6 AM, motorists should expect the following traffic impacts and closures:
- I-91 NB left lane closure from Exit 16 to the rest area
- I-691 EB left lane closure from Exit 1B to Exit 1