DAYTIME WORK
From 6:00 AM to 2:30 PM: crews will conduct the following activities:
Monday, October 6 through Friday, October 17:
- Steel repairs throughout the project
- Concrete sealing throughout the project
- Lighting installation at the truck stop
NIGHTTIME WORK
From 8:30 PM to 6:30 AM, crews will conduct the following activities:
Sunday, October 5 through Friday, October 17:
- Paving on I-91 NB
- Back up paving and building the snow shelf at I-91 NB to Route 66 EB
- Drain cleaning throughout the project
- Installing safety markings
- Sign installation
Sunday, October 12 through Friday, October 17:
- Drain cleaning throughout the project
TRAFFIC IMPACTS:
Nighttime Impacts—From 8:30 PM to 6:00 AM, motorists can expect the following traffic impacts:
Sunday, October 5 through Friday, October 17 (excluding Saturday nights):
- Lane closures along I-91 NB
- Lane closures along I-691 EB
- Lane and ramp closure of the I-691 EB Exit 1A off ramp to I-91 NB