Phase 1: Update for the Weeks of October 19 & 26, 2025

DAYTIME WORK

From 6:00 AM to 2:30 PM: crews will conduct the following activities:
Monday, October 20 through Friday, October 31:

  • Punch list activities throughout the project
  • Lighting installation at the truck stop

Monday, October 27 through Friday, October 31:

  • Concrete sealing throughout the project

NIGHTTIME WORK

From 8:30 PM to 6:30 AM, crews will conduct the following activities: Sunday, October 19 through Thursday, October 23:

  • Paving on I-91 NB
  • Drain cleaning throughout the project
  • Installing safety markings and line striping

TRAFFIC IMPACTS:

Nighttime Impacts—From 8:30 PM to 6:00 AM, motorists can expect the following traffic impacts:
Sunday, October 19 through Friday, October 23:

  • Lane closures along I-91 NB
  • Possible Route 15 NB ramp closure to I-91 NB
Next Post
One-Lane Varying Traffic Shifts on East Main Street Bridge Start Monday, 10/20/2025
Previous Post
Phase 2: Bridge Work on the I-691 Bridge over Gravel Street to Begin on Monday, October 20, 2025