DAYTIME WORK
From 6:00 AM to 2:30 PM: crews will conduct the following activities:
Monday, October 20 through Friday, October 31:
- Punch list activities throughout the project
- Lighting installation at the truck stop
Monday, October 27 through Friday, October 31:
- Concrete sealing throughout the project
NIGHTTIME WORK
From 8:30 PM to 6:30 AM, crews will conduct the following activities: Sunday, October 19 through Thursday, October 23:
- Paving on I-91 NB
- Drain cleaning throughout the project
- Installing safety markings and line striping
TRAFFIC IMPACTS:
Nighttime Impacts—From 8:30 PM to 6:00 AM, motorists can expect the following traffic impacts:
Sunday, October 19 through Friday, October 23:
- Lane closures along I-91 NB
- Possible Route 15 NB ramp closure to I-91 NB