DAYTIME WORK

From 6:00 AM to 2:30 PM: crews will conduct the following activities:

Monday, September 22 through Friday, September 26:

  • Bridge joint work at I-91 NB over Bee Street

Monday, September 22 through Friday, October 3:

  • Steel repairs throughout the project
  • Concrete sealing throughout the project
  • Lighting installation at the truck stop

NIGHTTIME WORK

From 8:30 PM to 6:30 AM, crews will conduct the following activities:

Sunday, September 21 through Friday, October 3:

  • Paving and building the snow shelf at I-91 NB to Route 66 EB
  • Drain cleaning along I-691 EB
  • Installing safety markings
  • Sign installation

Sunday, September 28 through Friday, October 3:

  • Membrane installation on I-91 NB over Bee Street

TRAFFIC IMPACTS:

Nighttime Impacts—From 8:30 PM to 6:00 AM, motorists can expect the following traffic impacts from Sunday, September 21 through Friday, October 3 (excluding Saturday nights):