Planned Construction Activities the Week of April 8, 2024

During the weekdays, Monday, April 8 through Friday, April 12, from 7:00 AM to 3:30 PM crews will conduct a variety of work as noted below on Route 15 NB from Miller Avenue to I-91, Rt. 15 NB ramp to I-691 WB and I691 WB to Broad Stret

  • Tree Cutting
  • Clearing and Harvesting Vegetation
  • Installing Erosion and Sedimentation Controls
  • Grubbing Excavation
  • Construction Sign Installations
  • Surveying

All this work will be mainly off the roadway with the follow traffic interferences noted below.

  • Shoulder Closures between 9 am and 3 pm on RT. 15 NB
  • Right Lane and Shoulder Closures between 9 am and 3 pm on I-91 NB and I-691 WB

During nights, Monday, April 8 through Friday, April 12, from 9:00 PM to 6:00 AM, crews will conduct a variety of work as noted below on Route 15 NB from Miller Avenue to I-91, Rt. 15 NB ramp to I-691 WB and I691 WB to Broad Street.

  • Clearing and Harvesting Vegetation

 

*****Special Closure On Monday, April 8*****

Route 15 Northbound:

  • East Main Street on-ramp to Route 15 NB, I-91 NB, & I-691 WB Ramp closure – see detour map below

Route 15 Southbound:

  • Right lane closure (Baldwin Avenue to the on-ramp from I-691 EB)