During weekdays, March 25 through Thursday, March 28, from 7:00 AM to 3:30 PM, crews will conduct the following activities:
Closures:
- Shoulders closures along I-91, I-691, and Route 15
- Local road lane/shoulder closures
Sign Installation:
- Install post-mounted construction signs on local roads
- Install post-mounted construction signs on I-91, I-691, and Route 15
Site Clearing:
- Clearing and harvesting operations sitewide
- Furnish and Install silt fence site wide, following clearing
Surveying activities sitewide:
Equipment:
- Install Smart Work Zone equipment (anticipated completion by 3/28)
During weekdays, Monday, April 1 through Friday, April 5, from 7:00 AM to 3:30 PM, crews will conduct the above activities as well as performing test pits at future basin location south of the East Main Street ramp
Night work Monday, April 1 through Friday, April 5, from 7:00 PM to 6:00 AM includes:
- Maintenance and protection of traffic shoulder/lane closures ( I-91,I-691, and Route 15)
- Clearing and harvesting operations in limited access areas
The green lines on the map below depict the project limits discussed in this update.