Phase 3: Update for the Weeks of September 21 & 28, 2026

DAYTIME WORK:

Monday through Friday from 7:00 AM to 3:30 PM crews will conduct a variety of work as noted throughout the Phase 3 Project limits:

  • Maintain water handling at multiple sites of culvert rehabilitation
  • Culvert rehabilitation at multiple sites
  • Install drainage and retaining wall along Route 15 SB in the vicinity of the on-ramp from I-91 SB
  • Sawcut, excavate and backfill in the I-91 SB median from north end of project limits to Exit 17 for the added lane
  • Sawcut, excavate and backfill in the Route 15 SB median and the I-691 EB median
  • Construction staking sitewide
  • Install temporary and permanent cables north of Baldwin Ave.
  • Install parapet caps, curb, deck ends at the I-691 EB Bridge over Gravel Street
  • Install support of excavation at the Route 15 SB ramp to I-91 SB over the I-91 SB ramp to Route 15 SB and Route 15 SB
  • Install drainage on Route 15 SB south of Paddock Ave.

*DAYTIME LANE CLOSURES:

Monday through Friday (9/21 through 9/24) from 8:00 AM to 2:00 AM:

  • I-91 SB lane closures (Murdock Avenue to Exit 15) for shoulder reconstruction

*NIGHTTIME WORK:

Sunday through Friday nights from 7:00 PM to 6:00 AM crews will conduct a variety of work as noted:

  • Permanent median shoulder work on I-91 SB from Murdock Ave. to the southern project limits
  • Temporary paving and barrier set-up for water line trench on Murdock Ave.
  • Bridge work on the I-691 WB bridge over 91NB & SB
  • Stage 1 demolition of the Murdock Avenue bridge over 91 NB & SB

*NIGHTTIME LANE CLOSURES:

Sunday through Friday nights from 8:00 PM to 6:00 AM crews will conduct a variety of work with lane closes as noted:

  • I-91 SB (from Exit 17 to Exit 15) for median replacement work and sawcutting
  • I-91 SB (from Exit 19 to Baldwin Avenue) for electrical work
  • Route 15 SB  for bridge work  on the I-691 EB bridge over Route 15 NB & SB

NIGHTTIME ROAD CLOSURES:

Thursday night, September 24 from 12:00 AM to 6:00 AM

  • Murdock Avenue bridge vicinity for electrical work (detour routes will be posted)

NIGHTTIME WORK – BRIDGE DEMOLITION/CONSTRUCTION:

Sunday through Thursday nights from 8:00 PM to 6:00 AMPlease read information concerning our nighttime noise monitoring efforts here.

LONG TERM CLOSURES:

*Schedule is subject to change due to weather and other circumstances.

Hoe ram and removal of asphalt and concrete previously saw cut on 15SB shoulder median
Previous Post
Phase 2: Update for the Weeks of September 21 & 28, 2026