Phase 2: Update for the Weeks of June 17 & 23, 2024

NIGHT WORK

No Night Work during the week of June 17 due to the Travelers Championship
Week of June 23, 2024 from 8:00 PM to 6:00 AM

  • Drill and pin temporary barrier along Route 15NB
  • Remove metal beam rail on Route 15 NB
  • Remove rumble strip on I-691 WB right lane, and mill and pave
  • Shift traffic on I-691 WB, Route 15 NB Exit 68 W off ramp through the project limits
  • Remove pavement to subgrade in the median of Route 15 between Miller Ave. and Paddock Ave.
  • Sawcutting for road widening and drainage crossings at Route 15 NB
    Install drainage crossings on Route 15 NB

DAY WORK

During weekdays, Monday, June 17 through Friday, June 28, from 6:00 AM to 3:30 PM crews will conduct a variety of work as noted below throughout the I-91, I-691, Route 15 Interchange Phase 2 Project limits:

  • Maintenance and protection of traffic with lane and shoulder closures on I-91, I-691, and Route 15, and some local roads
  • Form subgrade for temporary ramp widening at Route 15 NB Exit 69 N-E ramp
  • Excavate to subgrade Route 15 NB Exit 68 W off ramp
  • Excavate and backfill, form subgrade for new ramp I-91 NB Exit 16, East Main Street on-ramp to Route 15 NB andI-91 NB, I-691 WB and the Route 15 NB Exit 67 off-ramp
  • Remove existing concrete pavement at the Route 15 NB detention basin and excavate and backfill to subgrade
  • Drill and pin temporary barrier along the Route 15 NB Exit 68 W off ramp
  • Survey
  • Remove metal beam rail at temporary barrier locations
  • Perform highway illumination repairs
  • Install temporary drainage at the detention basin area
  • Relocate overhead wires at Paddock Avenue