DAYTIME WORK—From 6:00 AM to 2:30 PM:
Crews will conduct the following activities, Monday, November 3 through Friday, November 7:
- Steel repairs throughout the project
- Punch list activities throughout the project
NIGHTTIME WORK—From 8:30 PM to 6:30 AM
Crews will conduct the following activities, Sunday, November 2 through Thursday, November 6:
- Sign installation
- Installing safety markings and line striping
- Punch list activities throughout the project
TRAFFIC IMPACTS:
Nighttime Impacts—From 8:30 PM to 6:00 AM, motorists can expect the following traffic impacts, Sunday, November 2 through Thursday, November 6:
- Possible lane closures along I-91 NB